History
Dream Birthed & Acquisition of Land
The year was 2008 when the dream blossomed in essentials as Dream Realty managed to acquire the land. The stakes were high and the challenges were defiant.
Dream Realty indulged into fitting and shaping the new market location to welcome traders and businesses with the highest level of market services.
2008
Start of Excavation Process
The year 2011 marked the start of the 10 meter deep excavation process which proved relatively easy up until the last few hard stop meters but they were overcome.
The project excavation was first confronted by an important seepage leak. Experts and special material were brought in from the USA to obstruct and tank the entire platform.
2011
First Concrete
Pouring
January 2012 witnessed the first concrete pouring into the foundation which signaled the fresh start of The Octagon.
The foundations, the 2 basements and the 4 upper floors namely a parking and retail area. Blocks A, B and C partially treated